Fusion between the steel sheet and glass coating is very important Glass-Fused-to-Steel tanks production steps because it directly affects the Glass-Fused-to-Steel tank service life. In order to provide a high-quality product to our clients, Shijiazhuang Zhengzhong Technology Co.,Ltd conduct very strict quality control from raw material to final product. Before mass production, raw material and small sample test need to be done to check the quality of raw material and fusion between coating and steel panel, if qualified then mass production will be carried out. Tanks are produced on the automatic production line, to make sure good and stable quality control. After the production all steel panels need to be tested by 1500V spark holiday test, all steel panels are 0 discontinuity.

CNC Laser Cutting

Inputting the Confirmed drawing into the computer, bolt holes and openings will be cut by CNC laser cutting machine automatically.

Traitement préalable de l'acier - Grenaillage

Pliage en arc

Grenaillage selon la norme SSPC SP10, la surface de l'acier est de couleur argentée

Après le grenaillage, le panneau en acier doit être plié en arc selon le diamètre du réservoir.

Émaillage automatique

Pulvérisation automatique d'un émail sur les deux côtés de la plaque d'acier. L'épaisseur du revêtement est contrôlée entre 230 micromètres et 450 micromètres.

Hochofen avec haute température

En brûlant la plaque d'acier à des températures de 820°C à 930°C dans le four après l'émaillage et le séchage, la réaction de fusion des interfaces est favorisée pour relier les deux matériaux.

Examen du produit

La vérification de la qualité doit être effectuée après la fabrication. Cela comprend l'épaisseur de la peinture, le test de vacuité, la cohérence des couleurs, etc.